2024-05-23

TOCFOptical film expansion project,The functional polyolefin hot melt adhesive production expansion project will be postponed to2025Year12moon

       Lushan new materials5moon13daily announcement,The company plans to terminate the implementation“TOCFOptical film expansion project”,and use the remaining raised funds to permanently replenish working capital.,At the same time,“Functional polyolefin hot melt adhesive production expansion project”Completion time is given by2024Year5month extended to2025Year12moon。

      Reasons for terminating the investment project:companyTOCFOptical film products are mainly used in lamination and packaging of various large-sized touch panels and display modules.。exist“TOCFOptical film expansion project”In the process of implementation,Changes have occurred in the economic environment and market demand,Reduced demand for large-sized screens such as education touch screens,And folding and flexible screen mobile phones、Demand for small-size display terminals such as new energy vehicles has increased significantly,The company's existingTOCFThe optical film production line can basically meet existing business needs。

       “Functional polyolefin hot melt adhesive production expansion project”The investment plan is based on the market environment at that time、Industry development trends and other factors。in recent years,The company's functional polyolefin hot melt adhesive granule shipments and sales revenue have maintained a steady growth rate.,Another investment project through initial public offering of stocks“Functional polyolefin hot melt adhesive technical transformation project”Already at2023Year10Monthly availability for scheduled use,Production capacity is gradually released,Currently able to meet existing domestic business needs。at the same time,In order to accelerate the promotion of global layout,Meet the development needs of functional polyolefin hot melt adhesive particles in overseas markets,The company sets up a factory in Malaysia,at present4A functional polyolefin hot melt adhesive production line enters the installation and commissioning stage。Based on the above reasons,According to actual market demand changes and the company's existing and planned production capacity,The company proactively slows down“Functional polyolefin hot melt adhesive production expansion project”overall investment progress,Unable to complete construction within planned time。